Pavement grinding work on Holman Road tonight

by | Aug 7, 2014

Seattle Department of Transportation crews were not able to complete overnight grinding work on Holman Road Northwest last night, so they will be doing it tonight. Work will happen between 9 p.m. tonight (Thursday) and 7 a.m. Friday.

The north side of Holman Road NW between NW 87th Street and 8th Avenue NW is closed for grinding and paving work, and traffic has been shifted to the south side of the road where one lane remains open in each direction. The lane closures and traffic reconfiguration will remain in place until Aug. 14.

Following completion of the north side of the roadway, on Aug. 14 the south side of Holman Road NW will then be closed for grinding and paving between Northwest 87th Street and Eighth Avenue Northwest. Traffic will be shifted to the north side of the roadway with one lane open in each direction until Friday, Aug. 22, when paving on the south side will be complete.

Residents are advised that nighttime work is scheduled to take place between 9 p.m. and 7 a.m. on Aug. 7, 13, 14 and 21. Paving work is weather dependent and scheduled dates are subject to change. In addition to this night work, crews will continue sidewalk and median work on Aug. 9 and 16, from 9 a.m. to 6 p.m.

Local bus access will be maintained for King County Metro’s Route 28 and RapidRide D Line. For information on bus service, look for Rider Alert notices at bus stops, visit Metro Online at https://metro.kingcounty.gov/alerts/, or call (206) 553-3000.

Recent Posts

New juried art show debuts at the 44th PhinneyWood Winter Festival 

New juried art show debuts at the 44th PhinneyWood Winter Festival 

Two-part screen printing workshop at Dabble November 9th and 16th

Two-part screen printing workshop at Dabble November 9th and 16th

A toast to Chardell Paine – celebrating 32 Years of community, laughter, and legendary Beer Taste Events

A toast to Chardell Paine – celebrating 32 Years of community, laughter, and legendary Beer Taste Events